Temporary works & site · Piling works

Bored pile: concrete volume, cage and pour calculator

Concrete and reinforcement quantities for a bored pile: theoretical and overbreak volume, trucks, tremie pour time, cage mass (longitudinal bars, helix or ligatures, spacers) and checks on cover, clear bar spacing and minimum steel. Elevation and section drawn to scale.

Standard: AS 2159 Cl 6 (cover, cage) · AS 3600 · tremie placement practice

Open the live calculator → All temporary works & site calculators

Inputs in the worked example

The live calculator starts with these values; change any of them and every result, check and diagram updates instantly.

InputValueUnit
Pile diameter0.9m
Pile length20m
Overbreak allowance15%
Cage length12m
Longitudinal bars12
Bar diameter24mm
Helix bar diameter12mm
Helix pitch200mm
Cover to helix75mm
Truck load7m³
Tremie pour rate25m³/h

Worked example — results

ResultValueUnit
Theoretical volume12.72m³
Volume incl. overbreak14.63m³
Trucks3
Pour time (tremie)0.6h
Cage mass (incl. 8 % laps/spacers)684kg
Clear bar spacing160mm
Longitudinal steel ratio0.85%
20 mcage 12 mØ0.9 m (×3 width)Ø900 mmSection: 12N24, N12 helix @ 200, cover 75Bored pile — elevation & sectionScale 1:15 at 180 mm print width0500 mm
Diagram for the worked example

Method, formulas and assumptions