Site investigation · Geophysics & monitoring

Blast vibration: site law regression and charge limits calculator

Regresses monitored peak particle velocities against scaled distance to find the site constants, then the maximum charge per delay that keeps a structure within its limit.

Standard: PPV = K(D/√W)^(−B) · AS 2187.2-2006 Appendix J guide limits

Open the live calculator → All site investigation calculators

Inputs in the worked example

The live calculator starts with these values; change any of them and every result, check and diagram updates instantly.

InputValueUnit
Distance to the structure120m
Proposed charge per delay20kg
Limit10 mm/s houses / low-rise residentialmm/s
Records: distance (m), charge per delay (kg), PPV (mm/s)30, 5, 16.20 45, 10, 16.61 60, 8, 7.69 80, 20, 10.58 100, 15, 6.29 120, 25, 7.49 150, 30, 6.28 200, 40, 4.55 250, 30, 2.32 300, 50, 2.82

Worked example — results

ResultValueUnit
Site exponent B = −slope1.57
Site constant K = 10^intercept1,031
Fit R²0.989
Design scaled distance D/√W26.83m/kg^½
Predicted PPV5.81mm/s
Scaled distance for the limit19.00m/kg^½
Maximum charge per delay (D/SD)²39.89kg
1101001e30.11101001e31e4Scaled distance (m/kg^½)PPV (mm/s)limit
Diagram for the worked example

Method, formulas and assumptions

Related site investigation calculators

For preliminary design and education. Check every result against the current standard and your own engineering judgement before use.