Construction & estimating · Cost & planning

Labour productivity & crew cost calculator

Man-hours, crew days, labour cost with on-costs, plant cost and unit rate for an activity.

Standard: Quantity / output rate · crew size · on-costs

Open the live calculator → All construction & estimating calculators

Inputs in the worked example

The live calculator starts with these values; change any of them and every result, check and diagram updates instantly.

InputValueUnit
Quantity450units
Output per worker-hour1.8units/h
Crew size4
Hours per day8h
Hourly rate58$/h
On-costs (super, insurance, leave)30%
Plant per day650$

Worked example — results

ResultValueUnit
Worker-hours250h
Crew-hours62.5h
Duration7.8days
Labour cost$18,850
Plant cost$5,200
Unit rate (labour)$41.89per unit
Total$24,050
2468100102030crew sizeduration (days)7.8 d
Diagram for the worked example

Method, formulas and assumptions

Related construction & estimating calculators

For preliminary design and education. Check every result against the current standard and your own engineering judgement before use.