Ground engineering · Groundwater & dewatering

Pumping test analysis (Cooper–Jacob straight line) calculator

Fits a straight line to late-time drawdown against log time in an observation well to give transmissivity and storage coefficient, and checks the u < 0.05 validity condition.

Standard: Cooper & Jacob (1946): T = 2.3Q/(4πΔs), S = 2.25Tt0/r², valid for u < 0.05

Open the live calculator → All ground engineering calculators

Inputs in the worked example

The live calculator starts with these values; change any of them and every result, check and diagram updates instantly.

InputValueUnit
Pumping rate10L/s
Distance to observation well30m
Use readings from time ≥20min
Readings: time (min), drawdown (m)1, 0.188 2, 0.321 3, 0.408 5, 0.525 8, 0.638 12, 0.735 20, 0.864 30, 0.965 50, 1.091 80, 1.203 120, 1.301 200, 1.440 300, 1.533 500, 1.665 800, 1.779 1200, 1.876

Worked example — results

ResultValueUnit
Δs per log cycle (slope)0.571m
Intercept0.120m
Fit R²1.000
Transmissivity 2.3Q/(4πΔs)0.003m²/s
Zero-drawdown time t00.617min
Storage coefficient 2.25Tt0/r²0.000
Check: u at first fitted time r²S/(4Tt)0.017
Result: transmissivity T0.003m²/s
1101001e31e400.511.5Time (min)Drawdown (m)
Diagram for the worked example

Method, formulas and assumptions

Related ground engineering calculators

For preliminary design and education. Check every result against the current standard and your own engineering judgement before use.