Construction & estimating · Site operations

Truck and loader fleet balance calculator

Truck cycle time, trucks needed to keep the loader busy, fleet production and hours to move a volume.

Standard: Cycle time · match factor · production

Open the live calculator → All construction & estimating calculators

Inputs in the worked example

The live calculator starts with these values; change any of them and every result, check and diagram updates instantly.

InputValueUnit
Volume to move (bank)12000m³
Truck capacity10m³
Haul distance2500m
Loaded speed25km/h
Empty speed35km/h
Load time3min
Dump time1.5min
Spot and delays1min
Loader bucket3.5m³
Bucket fill factor0.9
Loader cycle0.6min
Efficiency (50-min hour)0.83

Worked example — results

ResultValueUnit
Truck cycle15.79min
Trips per truck-hour3.15
Production per truck31.5m³/h
Loader output261.5m³/h
Trucks to match loader9
Fleet production261.5m³/h
Hours to complete45.9h
Load3 minHaul6.0 minDump1.5 minReturn4.3 minSpot1 min
Diagram for the worked example

Method, formulas and assumptions

Related construction & estimating calculators

For preliminary design and education. Check every result against the current standard and your own engineering judgement before use.