Ground engineering · Consolidation & preloading

Preloading with surcharge calculator

Surcharge needed so that primary settlement under the permanent load is removed by a target time, with the degree of consolidation achieved.

Standard: Terzaghi 1D consolidation · Tv–U relation

Open the live calculator → All ground engineering calculators

Inputs in the worked example

The live calculator starts with these values; change any of them and every result, check and diagram updates instantly.

InputValueUnit
Clay thickness8m
DrainageDouble
cv2m²/yr
Available time24months
mv0.41/MPa
Permanent fill pressure60kPa

Worked example — results

ResultValueUnit
Drainage path4.00m
Tv = cv t/Hdr²0.250
U(Tv)0.564
Final settlement under permanent load mv Δσ H192.0mm
Total pressure needed (qp/U)106.3kPa
Extra surcharge46.35kPa
fillclay H 8 msurcharge qs 106 kPaTv = 0.250 · U = 56.4% in 24 monthsrequired total pressure 46 kPa00.5limit 1.0Surcharge ≤ 100% of permanent load (practical)0.77 PASS