Construction & estimating · Roofing & framing
Timber wall framing take-off calculator
Lineal metres of studs, plates, noggins and jamb studs for a list of walls.
Standard: Studs at spacing + plates + noggins + jambs
Open the live calculator → All construction & estimating calculators
Inputs in the worked example
The live calculator starts with these values; change any of them and every result, check and diagram updates instantly.
| Input | Value | Unit |
|---|---|---|
| Walls: length (m), height (m), openings | 12, 2.7, 3 12, 2.7, 2 9, 2.7, 1 9, 2.7, 1 6, 2.4, 1 4.5, 2.4, 1 | |
| Stud spacing | 450 | mm |
| Add corner studs | Yes | |
| Double top plate | Yes | |
| Waste | 10 | % |
| Timber price | 6.5 | $/m |
| Labour | 45 | $/m of wall |
Worked example — results
| Result | Value | Unit |
|---|---|---|
| Wall length | 52.5 | m |
| Studs | 406 | m |
| Plates | 158 | m |
| Noggins | 53 | m |
| Jamb studs | 47 | m |
| Total incl. waste | 729 | m |
| Total | $7,103 |
Method, formulas and assumptions
- Studs per wall = ceil(L/spacing) + 1 + 2 per opening (+2 corners)
- Noggin rows ≈ ceil(H/1.35) − 1
- Lintels, bracing, tie-downs not included; size members to AS 1684
- Rates are example inputs only. Replace them with current supplier quotes and local labour rates.
Related construction & estimating calculators
- Roof sheeting & battens — Gable roof area from plan and pitch, sheet count and length, battens, screws and cost.
- Earthworks cut & fill — Volumes from cross-section areas, loose and compacted volumes, truck loads and a mass-haul diagram.
- Excavation, cart-away & disposal — Excavated bank volume with batters, bulking, backfill retained, truck loads, tonnes to tip and cost.
- Asphalt & pavement — Asphalt tonnes, tack coat and base course quantities and cost.
- Concrete materials estimate — Cement bags, sand, aggregate and water for site-mixed concrete by ratio, with wastage.
- Bar schedule & rebar weight — Reinforcement mass by bar mark, totals by diameter and tonnage to order.
For preliminary design and education. Check every result against the current standard and your own engineering judgement before use.