Construction & estimating · Earthworks & pavements

Excavation, cart-away & disposal calculator

Excavated bank volume with batters, bulking, backfill retained, truck loads, tonnes to tip and cost.

Standard: Bank → loose (bulking) · truck loads · tip fees

Open the live calculator → All construction & estimating calculators

Inputs in the worked example

The live calculator starts with these values; change any of them and every result, check and diagram updates instantly.

InputValueUnit
Length30m
Width12m
Depth2.5m
Batter (H:V, 0 = vertical)0.5
Bulking factor25%
Retained for backfill20% of bank
Truck capacity (loose)10m³
Bank density1.9t/m³
Excavation14$/m³
Cartage per load160$
Tip fee35$/t

Worked example — results

ResultValueUnit
Bank volume1,031m³
Loose volume1,289m³
Loose volume to dispose1,031m³
Truck loads104
Tonnes to tip1,568t
Total$85,940
$85,940excavationDig: $14,438Cartage: $16,640Tip: $54,863
Diagram for the worked example

Method, formulas and assumptions

Related construction & estimating calculators