Construction & estimating · Concrete & reinforcement
Concrete volumes & cost calculator
Volumes for footings, slabs, beams and columns, order quantity rounded to 0.2 m³, trucks and cost.
Standard: Element take-off · truck loads · pump
Open the live calculator → All construction & estimating calculators
Inputs in the worked example
The live calculator starts with these values; change any of them and every result, check and diagram updates instantly.
| Input | Value | Unit |
|---|---|---|
| Element, count, L (m), B (m), D (m) | Pad footings, 12, 1.8, 1.8, 0.6 Strip footing, 1, 64, 0.45, 0.5 Ground slab, 1, 18, 10, 0.12 Columns, 12, 0.4, 0.4, 3.0 Beams, 1, 60, 0.3, 0.4 | |
| Waste / over-order | 5 | % |
| Truck capacity | 6 | m³ |
| Concrete supply | 285 | $/m³ |
| Pump per truck | 180 | $ |
| Place & finish | 70 | $/m³ |
Worked example — results
| Result | Value | Unit |
|---|---|---|
| Pad footings (12) | 23.33 | m³ |
| Strip footing (1) | 14.40 | m³ |
| Ground slab (1) | 21.60 | m³ |
| Columns (12) | 5.76 | m³ |
| Beams (1) | 7.20 | m³ |
| Net volume | 72.29 | m³ |
| Order (incl. waste, 0.2 m³ steps) | 76.0 | m³ |
| Truck loads | 13 | |
| Total | $29,060 |
Method, formulas and assumptions
- V = n·L·B·D per row
- Rates are example inputs only. Replace them with current supplier quotes and local labour rates.
Related construction & estimating calculators
- Concrete materials estimate — Cement bags, sand, aggregate and water for site-mixed concrete by ratio, with wastage.
- Bar schedule & rebar weight — Reinforcement mass by bar mark, totals by diameter and tonnage to order.
- Formwork contact area — Formwork area for slabs, beams, columns and footing edges, ply sheets allowing for re-use, and cost.
- Reinforcement quantities & cost — Steel tonnage from a kg/m³ ratio or a bar list, with laps and waste, supply and fix cost.
- Earthworks cut & fill — Volumes from cross-section areas, loose and compacted volumes, truck loads and a mass-haul diagram.
- Excavation, cart-away & disposal — Excavated bank volume with batters, bulking, backfill retained, truck loads, tonnes to tip and cost.
For preliminary design and education. Check every result against the current standard and your own engineering judgement before use.